:::

Content

Title: Directions for Allocating Installed Capacity of Offshore Wind Potential Zones Ch
Date: 2025.05.15
Legislative: 1.On January 18, 2018, the Ministry of Economic Affairs issued Order No. 10704600230, promulgating the full text comprising 31 points, effective immediately.
2.On May 15, 2025, the Ministry of Economic Affairs issued Order No. 11405005560, amending Points 2, 5, 7, 9, 10, 16, 21, 23, and 26, as well as Annexes 1, 2, 2-1, 4, and 7 to Point 10, Annex 4 and Annex 12 to Point 21; the amendments took effect immediately.
Content: Chapter 1. General Provisions
Article 1 Purpose and Authorization
The Ministry of Economic Affairs (hereinafter referred to as MOEA) promulgates these Directions 
authorized by Articles 4 and 9 of the Renewable Energy  Development Act, Article 5 of the 
Regulations on the Installation of Renewable  Energy Power Generation Equipment, and Article 24 
of The Electricity Act.
The objective is to promote a steady and orderly development of offshore wind  energy 
corresponding with the construction of domestic fundamental  infrastructure in order to realize the 
offshore wind power targets effectively and  drive domestic industry development.

Article 2 Governing Authority
Directions shall be executed by the Energy Administration (hereinafter referred to as  EA), MOEA, 
or the Industrial Development Administration (hereinafter referred to as  IDA).

Article 3 Definition and Categories
For the purpose of these Directions:
a.    Project: Means a single potential zone that an applicant, who is an  electricity enterprise or a 
preparatory office of electricity company limited  by shares, applies to MOEA to enter into the 
installed capacity allocation.  Following the process of allocation, the project shall be classified 
into  various stages respectively and named as Qualified Project, Selection Project, Auction Project, 
or Allocated project.
b.    Qualified Project: Means a Project submitted by the applicant is not  expired or invalid 
pursuant to Article 9 or 12 of Directions of Application  for Offshore Wind Site Selection and has 
been reviewed and verified.
c.    Selection Project: Means a Qualified Project that participates in the Selection Procedure for 
"Commissioning in 2020" or "Commissioning in  2021 - 2025" within the installed capacity 
allocation
d.    Auction Project: Means a Qualified Project that has participated in the  Selection Procedure is 
scored a minimum of 60 points in Selection  Procedure but is not allocated all the Project’s total 
applied for installed  capacity and subsequently enters the Auction Procedure.
e.    Allocated Project: Means a Selected or Auction Project has been allocated  installed capacity 
in Selection or Auction Procedure.
f.    Commissioning Year: Refers to the year in which a project is installed with  grid connection 
and meter and prepares to enter into pre-commissioning  process.

Article 4 Selection and Auction Volume
MOEA shall execute the following procedures so as to allocate 5.5 GW of  installed capacity 
between 2020 and 2025:
a.     Selection Procedure
Depending on the Commissioning Year of the Project, MOEA shall  implement two procedures; 
“Commissioning in 2020” and  “Commissioning in 2021-2025”. Projects in each procedure will be 
scored,  and ranked. The highest ranked projects, within the capacity allotted to the  
commissioning period, will be allocated installed capacity.
Unless otherwise provided, 500 MW of capacity shall be allocated in the  procedure of 
“Commissioning in 2020” and 3 GW in the procedure of  “Commissioning in 2021-2025”.
b.     Auction Procedure
MOEA shall rank the Auction Projects based on their Feed-in-Tariff  (hereinafter referred to as FIT) 
price, and, subsequently, their  commissioning year indicated by the applicant from 2021-2025. 
Highest  ranked projects will be allocated capacity within remainder of the 5.5 GW  capacity after 
the capacity allocated in the Selection Procedure has been deducted.

Chapter 2. Selection Procedure
Article 5 Qualification of Selection Procedure
Projects will qualify for the Selection Procedure if they have been submitted by  an applicant to EA 
for registration and are not invalid or expired under  “Directions of Application for Offshore Wind 
Site Selection”.

Article 6 Project Scope on Grid Connection
Project capacity, commissioning year and connection points shall not exceed  those approved or 
announced in the letter issued by Taiwan Power Company  (hereinafter referred to as TPC).

Article 7 Project Scope on Environmental Concept
Project scope and capacity shall not exceed the conclusion from the latest  approval, conditional 
approval or recommendation of approval governed by the  Environmental Impact Assessment and 
Review Committee of the Environmental  Protection Administration of the Executive Yuan.

Article 8 Commissioning Year
The applicant may select one or more commissioning years and express the  willingness to divide 
capacity of project in the Selection Procedure for "Commissioning in 2021 - 2025".

Article 9 Commitment on Projects Planned for “Commissioning in 2021-2025”
(1) The applicant shall commit to the following terms in order to enter the procedure  for 
"Commissioning in 2021 - 2025":
a.     If the project plans for “Commissioning in 2021” or “Commissioning in  2022”, the 
applicant shall commit to providing a substantial supply chain plan with elaboration, proof, and the 
letter issued by IDA before December  31, 2018.
b.     If the project plans for “Commissioning in 2023”, “Commissioning in 2024” or 
“Commissioning in 2025”, the applicant shall commit to providing a
substantial supply chain plan with elaboration, proof, and the letter issued  by IDA before 
December 31, 2019.
c.     The applicant shall commit to adopting best available technology to avoid  or mitigate 
environmental impact.
d.     The applicant shall commit to allocating 3% of the electricity development  assistance 
funds, pursuant to Article 65 of The Electricity Act, to the  ecosystem integration and corporate 
social responsibility project.
(2)    The IDA shall publish its requirements for the supply chain plan and the substantial supply 
chain plans in (1) shall be published on the IDA website.

Article 10 Preparation and Submission
(1) The applicant shall tender the submission with 30 copies of the following  documents (refer to 
Appendix 1) and the electronic files, in person or by post  (based on the time of delivery on the 
delivery proof), to EA before 5:00 pm on  March 30, 2018:
a.    An "Application Form for Offshore Wind Potential Zones Installed  Capacity Allocation- 
Commissioning in 2020" or an "Application Form for Offshore Wind Potential Zones Installed 
Capacity Allocation  “Commissioning in 2021 - 2025". (Refer to Appendix 2 and 2-1)
b.    Maps illustrating the location, layout and the surrounding windfarms.
c.    Environmental impact statements and the approval, conditional approval or  the latest minutes 
of panel meeting which recommends to approve the  project issued by the Environmental Impact 
Assessment and Review  Committee of the Ministry of Environment of the  Executive Yuan.
d.    Letters issued by TPC with regard to the grid connection of renewable  power generation 
systems.
e.    Registration issued by EA under Direction of Application for Offshore  Wind Site Selection
f.    Proposal of Offshore Wind Potential Zones Installed Capacity Allocation on Selection 
Procedure. (Refer to Appendix 3)
g.    Project Data Collection and Usage Agreement (Refer to Appendix 4)
h.    Representative Authorization Letter (Refer to Appendix 5)
i.    Statement of Offshore Wind Potential Zones Installed Capacity Allocation (Refer to Appendix 
6)
j.    An applicant who applies for the Selection Procedure for "Commissioning in 2020" shall 
provide actual and substantial documents in order to prove  the progress of project.
(such as the submarine cable circuit planned course survey permit, the sea  area land use location 
permit, specific zones of non-first-grade coastal  conservation zones permit, underwater cultural 
heritage survey, opinion  reports, or agreement letters from the local government, fisheries and 
other  relevant parties, and other substantial proof related to wind farm  development, required for 
the electricity enterprise planning permit).
k.    An applicant who applies for Selection Procedure for "Commissioning in 2021 - 2025" shall 
propose an Offshore Wind Potential Zones Installed  Capacity Allocation Commitment (refer to 
Appendix 7) and the proof of  founding of each sponsor of the applicant.
l.    Other documents required by MOEA.

Article 11 Reviewing and Verifying
(1) The Selection Procedure includes qualification reviewing, verifying and scoring.  The 
procedure shall be divided into two procedures for “Commissioning in 2020”  and 
“Commissioning in 2021-2025” respectively according to the commissioning  year indicated by 
the applicant.
(2) MOEA shall notify the applicant to revise or supplement application or explain in  person 
within fixed time for any question raised by MOEA regarding to the  application submitted by the 
applicant.
(3) A project which fails to satisfy the qualification pursuant to Article 5 or submits  after the 
deadline provided in Article 10 shall not be accepted.
(4) Under following circumstances, MOEA shall notify the applicant to revise or  supplement the 
application within fixed time. If revising or supplementing are not  within fixed time or are 
incompliant with the requirements, the project shall not  be accepted.
a. Incompliant with Article 6 to 9.
b. Incomplete, missing or questionable application.
c. False or concealed information
d. Other conditions which require further explanation or supplementation.

Article 12 Calling the Panel Meeting
(1) For the Selection Procedure, MOEA shall call 19 to 27 panelists including  representatives of 
authorities, institutions who are experts or scholars of offshore  wind power engineering, finances, 
or other related expertise. The external panelists in meeting shall not be less than one third of the 
group.
(2) During a panel meeting, half of the panelists shall be in attendance and attend the  meeting in 
person.
(3) In any one of the following circumstances, a panelist shall recuse himself from  the meeting:
(I) Whether the panelist him/herself, his/her spouse, his/her relative within  three generations, or 
other relative who lives together, is involved with the  application.
(II) Within the last three years, the panelist him/herself or his/her spouse has  had relationship of 
employment, consulting or agency with the applicant or  the representative of the applicant.
(III) Within the last three years, the panelist him/herself or his/her spouse has  had a working 
relationship with the applicant or the representative of the  applicant as an employer/employee, a 
consultant, a principle, a mandatory,  or an agent.
(IV) Other than the preceding circumstances, the panelist him/herself or MOEA  identifies the 
unsuitability of being a panelist.
(4) In case of preceding circumstances or other unsuitable reasons, MOEA shall exclude the 
unsuitable panelist if the panelist does not recuse him/herself.

Article 13 Scoring Criteria
(1) For the Selection Projects planned for "Commissioning in 2021-2025", scoring must be awarded 
based on the following criteria during the panel meeting (selection items, detailed items, and key 
points of scoring as described in  Appendix VIII):
a.    Technical capabilities (60%): Divided into construction (25%), engineering  design (20%), 
operation and maintenance planning (15%).
b.    Financial capabilities (40%): Divided into financial soundness (30%),  associations with 
domestic financial institutions (10%).
(2) For the Selection Projects planned for "Commissioning in 2020”, in addition to  the preceding 
scoring criteria, the panelist shall examine project’s progress of the  permits (whether prepared, 
under review, or acquired) provided in Electricity Act,  Electrical Registration Regulations and 
relative regulations.
(3) A Selection Project shall be placed last in the ranking if it is scored a total of zero  points by 
panel meeting in any selection item.

Article 14 Ranking and Allocating Projects for “Commissioning in 2020”
(1)    The Selection Projects planned for "Commissioning in 2020" shall be scored and  ranked 
without consideration of the difference between geographic regions. The  project with the highest 
total scores shall be ranked in first place, the next ranked  the second, and so on. For Selection 
Projects with identical rankings, the project with higher scores in its "technical capabilities" shall 
have priority. If the scores  for "technical capabilities" are also identical, MOEA will conduct a 
random  drawing.
(2)    The volume of the Selected Procedure for "Commissioning in 2020" shall be 500  MW in 
principle. MOEA shall allocate the capacity from the highest ranked project to the project whose 
allocated capacity accumulated with preceding allocated projects reaches 500. MOEA may increase 
the 500 MW cap by up to an  additional 100 MW to accommodate the project which is the last 
ranked project  within 500 MW. Whereas the project is not located in Changhua area, it is not  
subject to 100 MW limitation.
(3)    The Selection Project which is not allocated the entire capacity due to the situation provided in 
(2) may forfeit the capacity already allocated and participate  in the Selection Procedure for 
“Commissioning in 2021-2025”or the Auction Procedure.
(4)    Projects which are not allocated capacity may participate in the Selection  Procedure for 
“Commissioning in 2021-2025” or the Auction Procedure.

Article 15 Ranking and Allocating Projects for “Commissioning in 2021-2025”
(1) The Selection Projects planned for "Commissioning in 2021-2025 " shall be  scored and ranked 
without consideration of the difference between geographic regions. The project with the highest 
total scores shall be ranked in first place, the  next ranked the second, and so on. For Selection 
Projects with identical rankings,  the project with higher scores in "technical capabilities" shall 
have priority. If the  scores for "technical capabilities" are also identical, the Selection Project 
planned  to commission earlier shall have priority. If the commissioning years are also  identical, 
MOEA will conduct a random drawing.
(2) The volume of Selection Procedure for "Commissioning in 2021-2025" shall be 3  GW in 
principle. MOEA shall allocate the capacity from the highest ranked  project to the project whose 
allocated capacity accumulated with preceding  allocated projects reaches 3 GW. MOEA may 
increase the 3 GW cap by up to an  additional 100 MW to accommodate the project which is the 
last ranked project  within 3 GW.
(3) The Selection Project which is not allocated the entire capacity due to the  situation described 
in (2) may forfeit the capacity already allocated and  participate in the Auction Procedure.
(4) Projects which are not allocated capacity may participate in the Auction  Procedure.

Article 16 Ceiling Capacity on Consortium
(1) In the Selection Procedure for “Commissioning in 2021-2025”, MOEA shall also  rank the 
consortium pursuant to the projects’rank.
(2) For the consortium ranked in first place, the ceiling capacity for all Selection  Projects 
submitted by the first- place consortium shall not exceed 40% of 3 GW.  The second place shall 
not exceed 30% of 3 GW, the third place not 20% of 3  GW. For the rest of the consortium their 
selection projects shall not exceed 10% of 3 GW.
(3) In case ceiling capacity satisfies all the Selection Projects submitted by the  ranked consortium, 
the rest of ceiling capacity shall be allocated to others but the  ceiling capacity is still subject to (2).
(4) In case ceiling capacity does not satisfy all the projects submitted by the ranked  consortium, 
MOEA shall deduct the allocated capacity from the consortium’s  lowest ranked project but may 
increase 100 MW to the deducted project in  consideration of the integrity and effectiveness of the 
windfarm.
(5) The Selection Project which is not allocated the entire capacity due to the  situation described 
in (4) may forfeit the allocated capacity and participate in the  Auction Procedure.
(6) Qualified projects which are owned by the same preparatory office, or of which  one of the 
sponsor or representative is the same shall be viewed as one  consortium.
(7) In case consortium described in the application does not match the record  proposed for 
registration under “Directions of Application for Offshore Wind Site  Selection”, MOEA shall 
verify and identify consortium pursuant to the record  registerd before December 18, 2017.

Article 17 Allocation Limitation
(1) Allocation shall be implemented based on the ranking, followed by the earliest  commissioning 
year, grid connection points and the sequence indicated by the  applicant.
(2) If there is no sufficient grid capacity in the earliest commissioning year indicated  by an 
applicant, MOEA shall allocate the capacity to next indicated  commissioning year.
(3) Capacity allocation shall not be outside of the grid connection points, capacity,  and the 
commissioning year indicated by an applicant.

Article 18 Projects Devision
(1) In the Selection Procedure for “Commissioning in 2021-2025”, if annual  announced grid 
capacity is insufficient to allocate entire project and an applicant  expresses the willingness to 
divide the project capacity, MOEA shall divide the insufficient part of project to next available grid 
connection points and year  unless insufficient part is less than 100 MW capacity.
(2) Under preceding circumstances, if there is no more available grid capacity prior  to 2025, 
allocated applicant shall agree to forfeit insufficient part of project.
(3) Under circumstances provided in (1), if an applicant expresses the unwillingness  to divide 
project capacity, the entire capacity shall be moved to the next grid  capacity available year unless 
no more available grid capacity prior to 2025. If so,  an applicant shall agree to forfeit entire 
allocated project capacity.
(4) An applicant who forfeits the capacity pursuant to (2) or (3) may participate in  the Auction 
Procedure.
(5) Transmission Company may moderate the outcome of allocation and division on  the grounds 
of feasibility, steadiness of transmission and layout of cables.

Article 19 Anouncement and Notification
(1) MOEA shall announce the outcome of ranking, allocation, and the rest of grid  capacity, as well 
as notify each allocated applicant of the commissioning year,  allocated capacity, and grid 
connection point. Allocated applicants, subsequently, shall complete the signing of Administrative 
Contract within fixed time indicated by MOEA. The Administrative Contract shall provide terms, 
included but not  limited to, the performance bond and penalties for breach of contract.
(2) MOEA shall notify the applicants who are not allocated in the Selection Procedure that they may 
participate in the Auction procedure before the deadline for submission.
(3) Other than the condition provided in Article 14(3), Article 15(3), Article 16(5), or Article 18(4), 
an allocated applicant who forfeit the allocated capacity shall not  participate in the Auction 
Procedure.

Chapter 3. The Auction Procedure
Article 20 Qualified Projects
(1) A Selection Project which is scored 60 or above but not allocated the entire  capacity of the 
project is qualified to participate in the Auction Procedure.
(2) Articles 5 to 8 apply to the Auction Procedure.

Article 21 Preparation and Submission of a Bid
(1) Applicants shall tender their submission by post (based on the time of delivery on  the delivery 
proof) or in person, to EA before 5:00pm on the deadline for  submission indicated by MOEA with 
sealed bidding form (See Appendix IX) into the inner bidding envelope (See Appendix X), 
notification described in Article 19  and the following documents into outer bidding envelope (See 
Appendix XI) with  the affixed seals or signatures of the applicant and the representative on the 
cover  of the envelope.
a. Auction Application Form
b. Maps illustrating the location, layout and the surrounding windfarms.
c. Environmental impact statements and the approval, conditional approval or the  latest panel 
minutes that recommends to approve the project issued by the  Environmental Impact Assessment 
and Review Committee of the Environmental  Protection Administration of the Executive Yuan.
d. Letters issued by TPC with regard to the grid connection of renewable power  generation 
systems.
e. Project Data Collection and Usage Agreement (Refer to Appendix 4) f. Representative 
Authorization Letter (Refer to Appendix 5)
g. Statement of Offshore Wind Potential Zones Installed Capacity Allocation (Refer  to Appendix 
6)
h. Other documents required by MOEA

Article 22 Requirement on Bidding Form
(1) Applicants shall tender a FIT price (NTD/kWh) with the number to an accuracy  of four 
decimal places.
(2) Applicants must follow the specified format of the bidding form and complete  each part with 
accurate and truthful information. Forms shall be completed by  using blue/black fountain pens, 
ballpoint pens which cannot be edited/erased, or  printers. If corrections must be made, please affix 
the seals of the applicant and  the representative next to the corrected ones.
(3) The names of the applicant and the representative shall be clearly stated on the  bidding forms, 
and the seals or signatures of the applicant and the representative  are also required.

Article 23 Bid Exchange and Revocation
(1) If there are missing or incomplete documents provided in Article 21, MOEA shall  notify the 
applicant to revise and supplement the application within a fixed time.  If not done so or document 
is incompliant with the requirements, application shall not be accepted.
(2) Application shall not be accepted if an applicant does not meet the qualification  provided in 
Article 20 or deadline for submission described in Article 21.
(3) Once the bidding form provided in Article 21 has been delivered to EA, it shall  not be 
exchanged, revised, or supplemented.
(4) Applicant may revoke the bidding by post or deliver the withdrawal letter to EA in person before 
5:00pm prior to bid opening. If not done so, the revocation is  invalid.

Article 24 Reviewing and Verifying
(1) The bid or bidding form shall be invalid if:
a. FIT price is not filled out by the way requested or is unclear.
b. It is a repeat or shill bid.
c. It is not prepared with the specific format provided or unclear on the  ground of damages.
d. It is not sealed or is torn which might influence bid opening.
e. It is unclear on the grounds of incorrect or false information.
f. It is unclear or without or incomplete seals or signature on the bid, bidding  form, envelope or on 
the modified ones.
g. There is more than one bidding forms sealed inside a bidding envelope.
h. Without indicating the applicant's name and address, or the name, address,  and phone number 
of the representative or sponsor on the cover of the  outer bidding envelope.
i. Bidding form is added with conditions or expiration.
j. Other significant defects verified by MOEA.
(2) In case the applicant does not fill out, provide more than one, or offer the price  higher than the 
FIT rate announced in the bidding year, the FIT price indicated by  an applicant shall be recognized 
as the FIT price announced in the bidding year.

Article 25 Bid Opening and Ranking
(1) An applicant or the representative of the applicant with Authorization Letter (See  Appendix 
XIII) may attend the bid opening in person.
(2) Without taking the difference between geographic regions into consideration, the  projects shall 
be ranked by FIT price. The lowest bid shall be ranked in first place,  the next lowest ranked the 
second, and so on. If ranked identically, MOEA shall  conduct a random drawing to determine the 
ranking.

Article 26 Allocation and Granted FIT Price
(1) MOEA shall allocate the capacity to ranked projects within the rest of 5.5 GW  capacity after 
the capacity allocated in the Selection Procedure has been deducted.
(2) Signed FIT price shall be recognized as the lowest one between the granted price  in the 
Auction Procedure and the announced FIT rate announced in the year of  signing the Power 
Purchase Agreement with TPC.
(3) Allocated applicant may supply electricity via direct supply or wheeling to end  users and shall 
report to the EA within one month after the contract signing date.  If an allocated applicant stops 
supplying electricity via direct supply or wheeling  and signs a new Power Purchase Agreement 
contract, applicant shall comply with  relevant energy regulations at that time and the contract 
price shall apply to  lowest price between the bidding price and the FIT rate announced in the year 
of  signing the Power Purchase Agreement with TPC.
(4) Other than the condition in terms of allocation capacity of 3 GW or verified by  MOEA, Article 
17 to Article 19 shall apply to the Auction procedure.

Chapter 4. Signing of the Administrative Contract
Article 27 Preparation and Submmission
(1) For applying for signing of Administrative Contract, allocated applicant shall  provide 
notification provided in Article 19 or 26, modified Proposal of Offshore  Wind Potential Zones 
Selection in accordance with the opinion from  panelists ,and sufficient performance bond before 
the deadline for submission  indicated by MOEA.
(2) If allocated applicant does not revise the document within fixed time indicated by  MOEA, 
MOEA shall void or revoke the outcome of allocation and deny the submission for signing of the 
Administrative Contract on the grounds that  allocated applicant submits the application after 
deadline for submission,  incompliant documents, or without sufficient performance bond.
(3) Administrative Contract provided in (1) shall be announced by MOEA separately.

Article 28 Performance Bond
(1) Projects planned for "Commissioning in 2020” will owe a performance bond  which shall be 
calculated by multiplying the total capacity by NT$4 million per 1 MW (a performance bond of 
NT$4 million/MW). The performance bond of  projects for “Commissioning in 2021-2025” shall 
be calculated by multiplying  the total capacity by NT$2 million per 1 MW (a performance bond of 
NT$2  million/MW).
(2) Allocated applicant may choose to pay their performance bond from one of the  following 
payment methods:
a. Cash
b. Promissory note or check issued by a financial institution
c. Certified check
d. Postal order
e. Central Government bonds(CGBs)
f. Certificate of deposit pledged to the procuring entity
g. Irrevocable stand-by letter of credit issued or confirmed by a bank h. Bank guarantee (included in 
Appendix XIV)
(3) Allocated applicants who choose to deposit payment for the performance bond in  cash shall 
make a deposit before the signing of the Administrative Contract. In  addition, a receipt shall be 
obtained as proof of performance bond payment. The  same applies to those who wish to submit 
payments for the performance bond  using other methods besides cash.
(4) One year after an applicant acquiring electrical license, or once after the contract  was 
terminated and MOEA verifies no further amount to be deducted, the rest of  the performance bond 
(without interest) or the bank guarantee shall be returned to  the bank or an applicant.
(5) Other details, such as the account information for depositing performance bond  payments, 
shall be announced by MOEA separately.

Article 29 Project Milestones and Penalties
(1) After signing Administrative Contract, MOEA shall issue the Offshore Wind
Power System Installation Agreement to allocated applicant.
(2) Allocated applicant shall acquire establishment permit provided in
Electricity Act and Electrical Registration Regulations before December 31, 2019  and work 
permit in the year committed by allocated applicant.
(3) If allocated applicant is liable to delay the acquirment of establishment permit up  to 12 months, 
the registration issued under “Directions of Application for  Offshore Wind Site Selection” shall be 
voided which shall not be subject to the  requirement provided in Article 12 Section 1 (s) under 
said Direction.
(4) MOEA shall void the work permits in which there is no progress in constructional  work within 
two years of obtaining their work permits.
(5) Allocated applicant fails to fulfill its commitments required in Article 9, the  penalty for breach 
of contract shall be processed according to Article 27 Section 3  of the Administrative Contract.
(6) An applicant who delays the process provided in (2) or (4) due to force majeure  or reasons not 
liable to the applicant, no later than 90 days before expiry of the  time limit, may apply for 
extension which shall be no longer than 6 months every  time.
(7) Allocated project and the signed Administrative Contract shall be revoked or invalid if the 
registration is invalid or expired provided in “Directions of  Application for Offshore Wind Site 
Selection”.

Chapter 5. Reserved Projects
Article 30 Qualification and Procedure
(1) If the registration is invalid provided in Article 27 (2), Article 29 (3), the signed  Administrative 
Contract is terminated, or other circumstances verified by MOEA,  the allocated capacity of 
project shall be released to next- ranked but not  allocated project in Selection Procedure. The 
same procedure applies to the  Auction Procedure.
(2) Reserved application which receives capacity allocation as described above shall acquire the 
establish permit within two years after capacity allocation. In addition,
reserved applicant shall commit to commissioning wind farm before the end of  2025 which is not 
subject to Article 12 Section 1(2) in “Directions of Application  for Offshore Wind Site Selection”.
(3) Articles provided in Chapter 2 to Chapter 4 are applicable to the performance  bond, the 
signing of the Administrative Contract, as well as other conditions.

Chapter 6. Supplemental Provisions
Article 31 Supplemental Provisions
Other matters not covered herein shall be processed according to relevant  legislations.