No Support JavaScript

Ministry of Economic Affairs R.O.C.(Taiwan)
Laws and Regulations Retrieving System

Print Time:113.11.25 07:43

Content

Title: Directions for Allocating Installed Capacity of Offshore Wind Potential Zones Ch
Date: 2018.01.18
Legislative: 1.Promulgated on January 18 , 2018
Content: Chapter 1.    General Provisions
Article 1 Purpose and Authorization
The Ministry of Economic Affairs (hereinafter referred to as MOEA)
promulgates these Directions authorized by Articles 4 and 9 of the
Renewable Energy Development Act, Article 5 of the Regulations on
the Installation of Renewable Energy Power Generation Equipment,
and Article 24 of The Electricity Act.
The objective is to promote a steady and orderly development of offshore
wind energy corresponding with the construction of domestic fundamental
infrastructure in order to realize the offshore wind power targets effectively
and drive domestic industry development.

Article 2 Governing Authority
Directions shall be executed by the Bureau of Energy (hereinafter referred
to as BOE), MOEA, or the Industrial Development Bureau (hereinafter
referred to as IDB).

Article 3 Definition and Categories
For the purpose of these Directions:
a. Project: Means a single potential zone that an applicant, who is an
electricity enterprise or a preparatory office of electricity company limited
by shares, applies to MOEA to enter into the installed capacity allocation.
Following the process of allocation, the project shall be classified into
various stages respectively and named as Qualified Project, Selection Project,
Auction Project, or Allocated project.
b. Qualified Project: Means a Project submitted by the applicant is not
expired or invalid pursuant to Article 9 or 12 of Directions of Application
for Offshore Wind Site Selection and has been reviewed and verified.
c. Selection Project: Means a Qualified Project that participates in the
Selection Procedure for "Commissioning in 2020" or "Commissioning
in 2021 - 2025" within the installed capacity allocation
d. Auction Project: Means a Qualified Project that has participated in the
Selection Procedure is scored a minimum of 60 points in Selection
Procedure but is not allocated all the Project’s total applied for installed
capacity and subsequently enters the Auction Procedure.
e. Allocated Project: Means a Selected or Auction Project has been
allocated installed capacity in Selection or Auction Procedure.
f. Commissioning Year: Refers to the year in which a project is installed
with grid connection and meter and prepares to enter into pre-commissioning
process.

Article 4 Selection and Auction Volume
MOEA shall execute the following procedures so as to allocate 5.5 GW
of installed capacity between 2020 and 2025:
a. Selection Procedure
Depending on the Commissioning Year of the Project, MOEA shall
implement two procedures; “Commissioning in 2020” and
“Commissioning in 2021-2025”. Projects in each procedure will be scored,
and ranked. The highest ranked projects, within the capacity allotted to the
commissioning period, will be allocated installed capacity. 
Unless otherwise provided, 500 MW of capacity shall be allocated in the
procedure of “Commissioning in 2020” and 3 GW in the procedure of
“Commissioning in 2021-2025”.  
b. Auction Procedure
MOEA shall rank the Auction Projects based on their Feed-in-Tariff
(hereinafter referred to as FIT) price, and, subsequently, their
commissioning year indicated by the applicant from 2021-2025. Highest
ranked projects will be allocated capacity within remainder of the 5.5 GW
capacity after the capacity allocated in the Selection Procedure has been
deducted.
 
Chapter 2.    Selection Procedure
Article 5 Qualification of Selection Procedure

Projects will qualify for the Selection Procedure if they have been
submitted by an applicant to BOE for registration and are not invalid or
expired under “Directions of Application for Offshore Wind Site Selection”.

Article 6 Project Scope on Grid Connection 
Project capacity, commissioning year and connection points shall not
exceed those approved or announced in the letter issued by Taiwan Power
Company (hereinafter referred to as TPC).

Article 7 Project Scope on Environmental Concept
Project scope and capacity shall not exceed the conclusion from the
latest approval, conditional approval or recommendation of approval
governed by the Environmental Impact Assessment and Review
Committee of the Environmental Protection Administration of the
Executive Yuan.

Article 8 Commissioning Year
The applicant may select one or more commissioning years and express
the willingness to divide capacity of project in the Selection Procedure
for "Commissioning in 2021 - 2025".
Article 9 Commitment on Projects Planned for “Commissioning in
2021-2025”
(1)    The applicant shall commit to the following terms in order to enter
the procedure for "Commissioning in 2021 - 2025":
a. If the project plans for “Commissioning in 2021” or “Commissioning
in 2022”, the applicant shall commit to providing a substantial supply
chain plan with elaboration, proof, and the letter issued by IDB before
December 31, 2018.
b. If the project plans for “Commissioning in 2023”, “Commissioning
in 2024” or “Commissioning in 2025”, the applicant shall commit to
providing a substantial supply chain plan with elaboration, proof, and
the letter issued by IDB before December 31, 2019.
c. The applicant shall commit to adopting best available technology to
avoid or mitigate environmental impact.
d. The applicant shall commit to allocating 3% of the electricity development
assistance funds, pursuant to Article 65 of The Electricity Act, to the ecosystem
integration and corporate social responsibility project.
(2)    The IDB shall publish its requirements for the supply chain plan and the
substantial supply chain plans in (1) shall be published on the IDB website.

Article 10 Preparation and Submission
(1) The applicant shall tender the submission with 30 copies of the
following documents (refer to Appendix 1) and the electronic files, in
person or by post (based on the time of delivery on the delivery proof),
to BOE before 5:00 pm on March 30, 2018: 
a. An "Application Form for Offshore Wind Potential Zones Installed
Capacity Allocation- Commissioning in 2020" or an "Application Form
for Offshore Wind Potential Zones Installed Capacity Allocation
“Commissioning in 2021 - 2025". (Refer to Appendix 2 and 2-1)
b. Maps illustrating the location, layout and the surrounding windfarms.
c. Environmental impact statements and the approval, conditional approval
or the latest minutes of panel meeting which recommends to approve the
project issued by the Environmental Impact Assessment and Review
Committee of the Environmental Protection Administration of the Executive
Yuan.
d. Letters issued by TPC with regard to the grid connection of renewable
power generation systems.
e. Registration issued by BOE under Direction of Application for Offshore
Wind Site Selection
f. Proposal of Offshore Wind Potential Zones Installed Capacity Allocation
on Selection Procedure. (Refer to Appendix 3)
g. Project Data Collection and Usage Agreement (Refer to Appendix 4)
h. Representative Authorization Letter (Refer to Appendix 5)
i. Statement of Offshore Wind Potential Zones Installed Capacity
Allocation (Refer to Appendix 6)
j. An applicant who applies for the Selection Procedure for
"Commissioning in 2020" shall provide actual and substantial documents
in order to prove the progress of project. 
(such as the submarine cable circuit planned course survey permit, the sea
area land use location permit, specific zones of non-first-grade coastal
conservation zones permit, underwater cultural heritage survey, opinion
reports, or agreement letters from the local government, fisheries and other
relevant parties, and other substantial proof related to wind farm development,
required for the electricity enterprise planning permit).
k. An applicant who applies for Selection Procedure for "Commissioning in
2021 - 2025" shall propose an Offshore Wind Potential Zones Installed
Capacity Allocation Commitment (refer to Appendix 7) and the proof of
founding of each sponsor of the applicant.
l. Other documents required by MOEA.

Article 11 Reviewing and Verifying
(1)  The Selection Procedure includes qualification reviewing, verifying and
scoring. The procedure shall be divided into two procedures for
“Commissioning in 2020” and “Commissioning in 2021-2025” respectively
according to the commissioning year indicated by the applicant.
(2)  MOEA shall notify the applicant to revise or supplement application
or explain in person within fixed time for any question raised by MOEA
regarding to the application submitted by the applicant.
(3)  A project which fails to satisfy the qualification pursuant to Article 5
or submits after the deadline provided in Article 10 shall not be accepted.
(4)  Under following circumstances, MOEA shall notify the applicant to
revise or supplement the application within fixed time. If revising or
supplementing are not within fixed time or are incompliant with the
requirements, the project shall not be accepted.  
a. Incompliant with Article 6 to 9.
b. Incomplete, missing or questionable application.
c. False or concealed information
d. Other conditions which require further explanation or supplementation.

Article 12 Calling the Panel Meeting
(1)  For the Selection Procedure, MOEA shall call 19 to 27 panelists
including representatives of authorities, institutions who are experts or
scholars of offshore wind power engineering, finances, or other related
expertise. The external panelists in meeting shall not be less than one
third of the group.
(2)  During a panel meeting, half of the panelists shall be in attendance and
attend the meeting in person.
(3)  In any one of the following circumstances, a panelist shall recuse
himself from the meeting:
(I)  Whether the panelist him/herself, his/her spouse, his/her relative
within three generations, or other relative who lives together, is involved
with the application.
(II)  Within the last three years, the panelist him/herself or his/her spouse
has had relationship of employment, consulting or agency with the
applicant or the representative of the applicant.
(III)  Within the last three years, the panelist him/herself or his/her spouse
has had a working relationship with the applicant or the representative
of the applicant as an employer/employee, a consultant, a principle, a
mandatory, or an agent.
(IV)  Other than the preceding circumstances, the panelist him/herself
or MOEA identifies the unsuitability of being a panelist.
(4)  In case of preceding circumstances or other unsuitable reasons, MOEA
shall exclude the unsuitable panelist if the panelist does not recuse him/herself.

Article 13 Scoring Criteria
(1)  For the Selection Projects planned for "Commissioning in 2021-2025",
scoring must be awarded based on the following criteria during the panel
meeting (selection items, detailed items, and key points of scoring as
described in Appendix VIII):
a. Technical capabilities (60%): Divided into construction (25%), engineering
design (20%), operation and maintenance planning (15%).
b. Financial capabilities (40%): Divided into financial soundness (30%),
associations with domestic financial institutions (10%).
(2)  For the Selection Projects planned for "Commissioning in 2020”, in
addition to the preceding scoring criteria, the panelist shall examine project’s
progress of the permits (whether prepared, under review, or acquired) provided
in Electricity Act, Electrical Registration Regulations and relative regulations.
(3)  A Selection Project shall be placed last in the ranking if it is scored a total
of zero points by panel meeting in any selection item.
Article 14 Ranking and Allocating Projects for “Commissioning in 2020” 
(1)  The Selection Projects planned for "Commissioning in 2020" shall be
scored and ranked without consideration of the difference between
geographic regions. The project with the highest total scores shall be ranked
in first place, the next ranked the second, and so on. For Selection Projects
with identical rankings, the project with higher scores in its "technical capabilities"
shall have priority. If the scores for "technical capabilities" are also identical,
MOEA will conduct a random drawing.
(2)  The volume of the Selected Procedure for "Commissioning in 2020"
shall be 500 MW in principle. MOEA shall allocate the capacity from the
highest ranked project to the project whose allocated capacity accumulated
with preceding allocated projects reaches 500. MOEA may increase the
500 MW cap by up to an additional 100 MW to accommodate the project
which is the last ranked project within 500 MW. Whereas the project is not
located in Changhua area, it is not subject to 100 MW limitation.
(3)  The Selection Project which is not allocated the entire capacity due to
the situation provided in (2) may forfeit the capacity already allocated and
participate in the Selection Procedure for “Commissioning in 2021-2025”or
the Auction Procedure.
(4)  Projects which are not allocated capacity may participate in the Selection
Procedure for “Commissioning in 2021-2025” or the Auction Procedure.

Article 15 Ranking and Allocating Projects for “Commissioning in 2021-2025”
(1)  The Selection Projects planned for "Commissioning in 2021-2025 " shall
be scored and ranked without consideration of the difference between
geographic regions. The project with the highest total scores shall be ranked
in first place, the next ranked the second, and so on. For Selection Projects
with identical rankings, the project with higher scores in "technical
capabilities"shall have priority. If the scores for "technical capabilities"
are also identical, the Selection Project planned to commission earlier
shall have priority. If the commissioning years are also identical,
MOEA will conduct a random drawing.
(2)  The volume of Selection Procedure for "Commissioning in 2021-2025"
shall be 3 GW in principle. MOEA shall allocate the capacity from the
highest ranked project to the project whose allocated capacity accumulated
with preceding allocated projects reaches 3 GW. MOEA may increase the
3 GW cap by up to an additional 100 MW to accommodate the project which
is the last ranked project within 3 GW.
(3)  The Selection Project which is not allocated the entire capacity due to
the situation described in (2) may forfeit the capacity already allocated
and participate in the Auction Procedure.
(4)  Projects which are not allocated capacity may participate in the
Auction Procedure.

Article 16 Ceiling Capacity on Consortium
(1)  In the Selection Procedure for “Commissioning in 2021-2025”, MOEA
shall also rank the consortium pursuant to the projects’ rank.
(2)  For the consortium ranked in first place, the ceiling capacity for all
Selection Projects submitted by the first- place consortium shall not exceed
40% of 3 GW. The second place shall not exceed 30% of 3 GW, the third
place not 20% of 3 GW. For the rest of the consortium their selection
projects shall not exceed 10% of 3 GW.
(3)  In case ceiling capacity satisfies all the Selection Projects submitted
by the ranked consortium, the rest of ceiling capacity shall be allocated
to others but the ceiling capacity is still subject to (2).
(4)  In case ceiling capacity does not satisfy all the projects submitted by
the ranked consortium, MOEA shall deduct the allocated capacity from
the consortium’s lowest ranked project but may increase 100 MW to the
deducted project in consideration of the integrity and effectiveness of the
windfarm.
(5)  The Selection Project which is not allocated the entire capacity due to
the situation described in (4) may forfeit the allocated capacity and participate
in the Auction Procedure.
(6)  Qualified projects which are owned by the same preparatory office, or
of which one of the sponsor or representative is the same shall be viewed
as one consortium.
(7)  In case consortium described in the application does not match the
record proposed for registration under “Directions of Application for
Offshore Wind Site Selection”, MOEA shall verify and identify consortium
pursuant to the record registerd before December 18, 2017.

Article 17 Allocation Limitation
(1)  Allocation shall be implemented based on the ranking, followed by the
earliest commissioning year, grid connection points and the sequence indicated
by the applicant.
(2)  If there is no sufficient grid capacity in the earliest commissioning year
indicated by an applicant, MOEA shall allocate the capacity to next indicated commissioning year.
(3)  Capacity allocation shall not be outside of the grid connection points,
capacity, and the commissioning year indicated by an applicant.

Article 18 Projects Devision
(1)  In the Selection Procedure for “Commissioning in 2021-2025”, if annual
announced grid capacity is insufficient to allocate entire project and an
applicant expresses the willingness to divide the project capacity, MOEA
shall divide the insufficient part of project to next available grid connection
points and year unless insufficient part is less than 100 MW capacity.
(2)  Under preceding circumstances, if there is no more available grid
capacity prior to 2025, allocated applicant shall agree to forfeit insufficient
part of project.
(3)  Under circumstances provided in (1), if an applicant expresses the
unwillingness to divide project capacity, the entire capacity shall be moved
to the next grid capacity available year unless no more available grid capacity
prior to 2025. If so, an applicant shall agree to forfeit entire allocated project
capacity.
(4)  An applicant who forfeits the capacity pursuant to (2) or (3) may
participate in the Auction Procedure.
(5)  Transmission Company may moderate the outcome of allocation and
division on the grounds of feasibility, steadiness of transmission and layout
of cables.

Article 19 Anouncement and Notification
(1)  MOEA shall announce the outcome of ranking, allocation, and the rest
of grid capacity, as well as notify each allocated applicant of the commissioning
year, allocated capacity, and grid connection point. Allocated applicants,
subsequently, shall complete the signing of Administrative Contract within
fixed time indicated by MOEA. The Administrative Contract shall provide
terms, included but not limited to, the performance bond and penalties for
breach of contract.
(2)  MOEA shall notify the applicants who are not allocated in the Selection
Procedure that they may participate in the Auction procedure before the
deadline for submission. 
(3)  Other than the condition provided in Article 14(3), Article 15(3),
Article 16(5), or Article 18(4), an allocated applicant who forfeit the
allocated capacity shall not participate in the Auction Procedure.

Chapter 3.    The Auction Procedure
Article 20 Qualified Projects

(1)  A Selection Project which is scored 60 or above but not allocated the entire
capacity of the project is qualified to participate in the Auction Procedure.
(2)  Articles 5 to 8 apply to the Auction Procedure.

Article 21 Preparation and Submission of a Bid
(1)  Applicants shall tender their submission by post (based on the time of
delivery on the delivery proof) or in person, to BOE before 5:00pm on the
deadline for submission indicated by MOEA with sealed bidding form (See
Appendix IX) into the inner bidding envelope (See Appendix X), notification
described in Article 19 and the following documents into outer bidding
envelope(See Appendix XI) with the affixed seals or signatures of the
applicant and the representative on the cover of the envelope.
a. Auction Application Form
b. Maps illustrating the location, layout and the surrounding windfarms.
c. Environmental impact statements and the approval, conditional approval
or the latest panel minutes that recommends to approve the project issued
by the Environmental Impact Assessment and Review Committee of the
Environmental Protection Administration of the Executive Yuan.
d. Letters issued by TPC with regard to the grid connection of renewable
power generation systems.
e. Project Data Collection and Usage Agreement (Refer to Appendix 4)
f. Representative Authorization Letter (Refer to Appendix 5)
g.    Statement of Offshore Wind Potential Zones Installed Capacity Allocation
(Refer to Appendix 6)
h. Other documents required by MOEA

Article 22 Requirement on Bidding Form
(1)  Applicants shall tender a FIT price (NTD/kWh) with the number to an
accuracy of four decimal places.
(2)  Applicants must follow the specified format of the bidding form and
complete each part with accurate and truthful information. Forms shall be
completed by using blue/black fountain pens, ballpoint pens which cannot
be edited/erased, or printers. If corrections must be made, please affix the
seals of the applicant and the representative next to the corrected ones.
(3)  The names of the applicant and the representative shall be clearly stated
on the bidding forms, and the seals or signatures of the applicant and the
representative are also required.

Article 23 Bid Exchange and Revocation
(1)  If there are missing or incomplete documents provided in Article 21,
MOEA shall notify the applicant to revise and supplement the application
within a fixed time. If not done so or document is incompliant with the
requirements, application shall not be accepted.
(2)  Application shall not be accepted if an applicant does not meet the
qualification provided in Article 20 or deadline for submission described
in Article 21.
(3)  Once the bidding form provided in Article 21 has been delivered to
BOE, it shall not be exchanged, revised, or supplemented.
(4)  Applicant may revoke the bidding by post or deliver the withdrawal
letter to BOE in person before 5:00pm prior to bid opening. If not done
so, the revocation is invalid.

Article 24 Reviewing and Verifying
(1)  The bid or bidding form shall be invalid if:
a. FIT price is not filled out by the way requested or is unclear.
b. It is a repeat or shill bid.
c. It is not prepared with the specific format provided or unclear on the
ground of damages.
d. It is not sealed or is torn which might influence bid opening.
e. It is unclear on the grounds of incorrect or false information.
f. It is unclear or without or incomplete seals or signature on the bid, bidding
form, envelope or on the modified ones.
g. There is more than one bidding forms sealed inside a bidding envelope.
h. Without indicating the applicant's name and address, or the name, address,
and phone number of the representative or sponsor on the cover of the outer
bidding envelope.
i. Bidding form is added with conditions or expiration.
j. Other significant defects verified by MOEA.
(2)  In case the applicant does not fill out, provide more than one, or offer
the price higher than the FIT rate announced in the bidding year, the FIT
price indicated by an applicant shall be recognized as the FIT price announced
in the bidding year.

Article 25 Bid Opening and Ranking
(1)  An applicant or the representative of the applicant with Authorization
Letter (See Appendix XIII) may attend the bid opening in person.
(2)  Without taking the difference between geographic regions into
consideration, the projects shall be ranked by FIT price. The lowest bid shall
be ranked in first place, the next lowest ranked the second, and so on. If
ranked identically, MOEA shall conduct a random drawing to determine
the ranking.

Article 26 Allocation and Granted FIT Price
(1)  MOEA shall allocate the capacity to ranked projects within the rest
of 5.5 GW capacity after the capacity allocated in the Selection Procedure
has been deducted.
(2)  Signed FIT price shall be recognized as the lowest one between the
granted price in the Auction Procedure and the announced FIT rate announced
in the year of signing the Power Purchase Agreement with TPC.
(3)  Allocated applicant may supply electricity via direct supply or wheeling
to end users and shall report to the BOE within one month after the contract
signing date. If an allocated applicant stops supplying electricity via direct
supply or wheeling and signs a new Power Purchase Agreement contract,
applicant shall comply with relevant energy regulations at that time and the
contract price shall apply to lowest price between the bidding price and the
FIT rate announced in the year of signing the Power Purchase Agreement
with TPC.
(4)  Other than the condition in terms of allocation capacity of 3 GW or
verified by MOEA, Article 17 to Article 19 shall apply to the Auction procedure.

Chapter 4.    Signing of the Administrative Contract
Article 27 Preparation and Submmission 

(1)  For applying for signing of Administrative Contract, allocated applicant
shall provide notification provided in Article 19 or 26, modified Proposal
of Offshore Wind Potential Zones Selection in accordance with the opinion
from panelists ,and sufficient performance bond before the deadline for
submission indicated by MOEA.
(2)  If allocated applicant does not revise the document within fixed time
indicated by MOEA, MOEA shall void or revoke the outcome of allocation
and deny the submission for signing of the Administrative Contract on the
grounds that allocated applicant submits the application after deadline for
submission, incompliant documents, or without sufficient performance bond.
(3)  Administrative Contract provided in (1) shall be announced by MOEA
separately.

Article 28 Performance Bond
(1)  Projects planned for "Commissioning in 2020” will owe a performance
bond which shall be calculated by multiplying the total capacity by NT$4
million per 1 MW (a performance bond of NT$4 million/MW). The
performance bond of projects for “Commissioning in 2021-2025” shall be
calculated by multiplying the total capacity by NT$2 million per 1 MW
(a performance bond of NT$2 million/MW).
(2)  Allocated applicant may choose to pay their performance bond from
one of the following payment methods:
a. Cash
b. Promissory note or check issued by a financial institution
c. Certified check
d. Postal order
e. Central Government bonds(CGBs)
f. Certificate of deposit pledged to the procuring entity
g. Irrevocable stand-by letter of credit issued or confirmed by a bank
h. Bank guarantee (included in Appendix XIV)
(3)  Allocated applicants who choose to deposit payment for the performance
bond in cash shall make a deposit before the signing of the Administrative
Contract. In addition, a receipt shall be obtained as proof of performance
bond payment. The same applies to those who wish to submit payments for
the performance bond using other methods besides cash.
(4)  One year after an applicant acquiring electrical license, or once after
the contract was terminated and MOEA verifies no further amount to be
deducted, the rest of the performance bond (without interest) or the bank
guarantee shall be returned to the bank or an applicant.
(5)  Other details, such as the account information for depositing performance
bond payments, shall be announced by MOEA separately.

Article 29 Project Milestones and Penalties
(1)  After signing Administrative Contract, MOEA shall issue the Offshore
Wind Power System Installation Agreement to allocated applicant.
(2)  Allocated applicant shall acquire establishment permit provided in
Electricity Act and Electrical Registration Regulations before December 31, 2019
and work permit in the year committed by allocated applicant.
(3)  If allocated applicant is liable to delay the acquirment of establishment
permit up to 12 months, the registration issued under “Directions of Application
for Offshore Wind Site Selection” shall be voided which shall not be subject
to the requirement provided in Article 12 Section 1 (s) under said Direction.
(4)  MOEA shall void the work permits in which there is no progress in
constructional work within two years of obtaining their work permits.
(5)  Allocated applicant fails to fulfill its commitments required in Article 9,
the penalty for breach of contract shall be processed according to Article 27
Section 3 of the Administrative Contract.
(6)  An applicant who delays the process provided in (2) or (4) due to force
majeure or reasons not liable to the applicant, no later than 90 days before
expiry of the time limit, may apply for extension which shall be no longer
than 6 months every time.
(7)  Allocated project and the signed Administrative Contract shall be revoked
or invalid if the registration is invalid or expired provided in “Directions of
Application for Offshore Wind Site Selection”.

Chapter 5.    Reserved Projects
Article 30 Qualification and Procedure

(1)  If the registration is invalid provided in Article 27 (2), Article 29 (3),
the signed Administrative Contract is terminated, or other circumstances
verified by MOEA, the allocated capacity of project shall be released to
next- ranked but not allocated project in Selection Procedure. The same
procedure applies to the Auction Procedure.
(2)  Reserved application which receives capacity allocation as described
above shall acquire the establish permit within two years after capacity
allocation. In addition, reserved applicant shall commit to commissioning
wind farm before the end of 2025 which is not subject to Article 12 Section 1(2)
in “Directions of Application for Offshore Wind Site Selection”.
(3)  Articles provided in Chapter 2 to Chapter 4 are applicable to the
performance bond, the signing of the Administrative Contract, as well as
other conditions.

Chapter 6.    Supplemental Provisions
Article 31 Supplemental Provisions

Other matters not covered herein shall be processed according to relevant
legislations.

 
Data Source:Ministry of Economic Affairs R.O.C.(Taiwan) Laws and Regulations Retrieving System