Article 1
These Regulations are enacted pursuant to Paragraph 4 of Article 4 of the Reclaimed Water
Resources Development Act (hereinafter referred to as the "Act").
Article 2
Regions with the likelihood of undersupply of water resources referred to in Article 4 of
the Act shall mean such regions whose supply and demand analysis in the Regional Water Resources
Master Plan, have been reviewed by the central competent authority in water source development
status, overall water supply allocation measures, systemic reclaimed water development potential
and other relevant factors, and which are announced by the central competent authority as the
available water quantities that fail to fulfill the demand water quantity for the target year.
Article 3
The municipal or county (city) competent authority of regions with the likelihood of undersupply
of water resources shall regularly announce the public sewer system's total quantity of wastewater
(sewage) or effluent water, its available quantity for application, and related information within
the jurisdiction on a yearly basis.
Article 4
If the initiated development is located in a region with the likelihood of undersupply of water
resources, and the water intake quantity in the water consumption plan reaches 3,000 cubic meters
per day or more, the developer shall use systemic reclaimed water pursuant to the water consumption
plan approved by the central competent authority.
For a water consumption plan approved prior to the promulgation of these Regulations, if the
scheduled water intake quantity in the water consumption plan cumulatively reaches 3,000 cubic
meters per day or more due to modified development, the increased portion of the quantity shall use
systemic reclaimed water pursuant to the water consumption plan review result.
The certain percentages of systemic reclaimed water that shall be used pursuant to the preceding
two Paragraphs are as follows. If the water consumption includes domestic, other and industrial water
consumption, the quantity of systemic reclaimed water that shall be used daily may be calculated
altogether:
1.For domestic and other water consumption in the water consumption plan, 10% or more of systemic
reclaimed water shall be used.
2.For industrial water consumption in the water consumption plan, 50% or more of systemic reclaimed
water shall be used.
If according to the preceding Paragraph to calculate, the quantity of systemic reclaimed water shall
be used daily is less than 1,000 cubic meters per day, such may be exempted from using systemic
reclaimed water according to the provisions of the preceding Paragraph.
The central competent authority shall approve the systemic reclaimed water usage schedule and
corresponding water quantity in Paragraphs 1 and 2 on the basis of the development, during the development
and operation period which, is located in a water supply area where the government has initiated a
Reclaimed Water Development Project; as well as the percentage of systemic reclaimed water to be used
in Paragraph 3 may be adjusted, depending on the supply conditions for the sewer system and the
Reclaimed Water Development Project.
Identification of whether such initiated or modified development is located in a region with the
likelihood of undersupply of water resources or not shall be subject to the central competent authority's
latest announcements during the review period for such a water consumption plan.
Article 5
Where the actual water consumption deviates from the water consumption plan to the certain percentage
or certain size stipulated in Paragraph 2 of Article 4 of the Act shall mean that after the central
competent authority's audit, the actual water consumption has not reached 70% of the approved water
intake quantity for (3) three consecutive years and the discrepancy reaches an average of 3,000
cubic meters per day or more.
A developer meeting the requirements of the preceding Paragraph shall submit a variance analysis
report to the central competent authority for review. The central competent authority may, depending
on its discrepancy, adjust or reduce the originally approved yearly and final water usage plan in
the water consumption plan, or adjust the certain percentage of systemic reclaimed water to be used
within the range of variance.
The adjustment of the certain percentage of systemic reclaimed water to be used in the preceding
Paragraph shall be deliberated and determined on a case-by-case basis by the central competent authority,
after evaluating the water supply conditions, industrial water consumption characteristics, the
developer's water-saving efficiency, the construction status of adjacent public sewer systems and
reclaimed water plants, and other relevant factors. Such percentage shall be lower than the percentages
specified in Paragraph 3 of the preceding Article.
Article 6
For a water consumption plan submitted according to Paragraph 6 of Article 54-3 of the Water Act,
in a region with the likelihood of undersupply of water resources, if the water intake quantity
in the water consumption plan cumulatively reaches 3,000 cubic meters per day or more due to the
increase or change of the water quantity beyond the existing water intake demand, the increased
water quantity portion shall use the certain percentage for systemic reclaimed water pursuant to
the water consumption plan review result. The provisions in Paragraph 3 of Article 4, shall be
applicable mutatis mutandis.
Article 7
A developer that is to use systemic reclaimed water may exchange water sources with an existing
water intake enterprise in the same region with the likelihood of undersupply of water resources,
as a substitute for fulfilling its obligation to use the systemic reclaimed water,
The developer and the substitute performer shall first submit a water consumption plan and a
notarized alternative-performance contract to the central competent authority for review; only
after such contract is approved may it be performed.
The water consumption plan proposed by the substitute performer in the preceding Paragraph shall
contain the actual water intake records and the use permit for wastewater (sewage) or effluent
water as specified in Article 11 of the Act or the reclaimed water purchase contract between the
substitute performer and the Reclaimed Water Operator.
Article 8
These Regulations become effective as of the date of promulgation.
|